TRESIA · CASE STUDY · LIVORNO, JANUARY 2026

Exceptional project cargo transport on the FI-PI-LI

On the night of 5–6 January 2026, from 22:00 to 06:00, TRESIA coordinated the exceptional transport of two large industrial silos along the Florence–Pisa–Livorno highway (S.G.C. FI-PI-LI), with a temporary closure of the section between the Livorno Aurelia–Stagno junction (km 77+000) and the Livorno Porto junction (km 79+400), in both directions.

Height

Over 6.00 metres

Width

Over 5.50 metres

Weight

Over 100,000 kg each

Destination

Industrial plant in the Stagno area (Livorno)

An operation with high infrastructure impact

The two silos were oversized exceptional loads with particularly demanding characteristics. To ensure traffic safety and minimise disruption, all traffic was diverted onto ordinary roads, with temporary advance signage and alternative routes agreed with the competent authorities.

TRESIA’s role: technical coordination and logistics engineering

TRESIA handled the technical, logistical, operational and permitting coordination of the entire operation: from the preliminary route survey (geometry, available heights, infrastructure interference) to night-time planning and the coordination of technical escorts and safety activities along the road. Permits and escorts were managed through TRESIA’s specialised department, TRESIA Connect.

The road transport itself was carried out by Autotrasporti Torri, an operator specialised in oversized and overweight loads.

Covered by local and regional media

The operation was reported by local and regional news outlets, including Dai Colli Fiorentini, with an article on the transport coordinated by TRESIA, and Il Tirreno, which reported the date, times and arrangements for the closure (articles in Italian).

Project cargo and exceptional transport for industry

Operations like this show that moving large industrial components requires an integrated approach combining engineering skills, regulatory knowledge, coordination with multiple authorities and operational capability on the ground. TRESIA supports industrial companies, EPC contractors and logistics operators from the study phase through to final delivery on site.

See also: silo and tank transport, project cargo and the case study on the 55-tonne hydroelectric turbine.

Have a large component to move?

Send us dimensions, weight and route: we will assess vehicle, permits and timing.

Contact TRESIA
Scroll to Top